Kitchen Refresh

The Kitchen Refresh of 2015

WEEK SEVEN

Countertop has been set in place, with stainless sink, and range hood.
All door handles are installed. A new oven cabinet replaces original that included a slight defect.
CounterTopInstalled

WEEK SIX

All the cabinetry has been installed in place.
Except oven cabinet that is being replaced due to an annoying defect
Ready for counter top installation.

CabinetsInstalled

New sliding door has been installed.
Tough, tight fit with awning at the top.

SliderInstalled

The butcher block has been refurbished and replaced,
perhaps the sole item that will remain from old kitchen.

ButcherBlockReInstalled

WEEK FOUR

Lower, counter top cabinets are set in place, preparing for countertop templating.
Ceilings and some walls painted.
CounterCabsInPlace

WEEK THREE

LED can lights, and switches and plugs relocated and installed.
New sheetrock is installed, taped and textured.
Now it has to dry.

WallTexture1WallTexture2

WEEK TWO

Old cabinetry hauled away and recycled.

RecyclingOldCabinets

Plumbing work for the sink and dishwasher

SinkPlumbingSinkPlumbing2

WEEK ONE

Patio Full of Cabinets – Donated to Habitat
PatioFullOfCabinets-001
Where the sink and cooktop used to be.

CountertopWall-001

On the left was the double oven, on the right, the sink.
In the middle will be a lazy susan.
OvenAndSinkCorner-001
Refrigerator nook, backs up to bathroom.
BehindRefridgerator-001
Replumbed water for upstairs shower, heat ducts, new can light, rerouting wires.
ReplumbedShowerLines-001
All the old stuff is gone.
ItsAllGone-001

And so it begins……

DAY 1

Removing butcher block island, cabinets, cooktop, jennair.
Starting to reveal all that is underneath.

ButcherBlock_1-001
ButcherBlock_2-001
CookingArea_1-001 CookingArea_2-001 Cooktop_1-001 Cook Jennair_1-001 Jennair_2-001

 